A new museum

Project Timeline

2018

June 2018 | First proposal by Mikaël Seban, architect specialized in museum renovations
December 2018 | Start of the architectural competition

2019

June 2019 | First architectural jury : 65 teams applied, 4 selected for the second stage of the competition
October 2019 | Approval by the City Council of the Museum's Strategic Plan for 2020-2025

2020

January 2020 | The team led by Atelier Novembre is declared the winner of the competition
June 2020 | start of the preliminary architectural surveys
Automn 2020 | start of the archeological surveys

2021

End of the architectural surveys, launch of the public procurement procedures

2022 - 2023

Construction is planned on the first section

2024

Inauguration of the first section of the museum renovation